PLEASE NOTE, BID SUBMITTAL HAS BEEN POSTPONED UNTIL FEBRUARY 15, 2013.
Approximately 7,800 /- linear feet of new asphalt surfaced recreation path construction. The project will include earthwork, drainage improvements, two new bridges over Ten Mile Creek and revegetation work, as described in the plan set dated: November 27, 2012.
|
|
|
| 1/11/2013 12:00 AM
|
|
|
| PLEASE NOTE, BID SUBMITTAL HAS BEEN POSTPONED UNTIL FEBRUARY 15, 2013.
|
|
|
| 2/15/2013 1:00 PM
|
|
|
| January 22, 2013 (Mandatory)
|
|
|
| Brad Eckert, 970.668.4213
|
|
|
| yes, see below
|
|
|
| M-F 8:00 a.m. - 5:00 p.m.
|
|
|
Invitation to bid STE 610-015 Ten Mile Canyon Recpath Geotech Report Addendum 1
Addendum 2
|
|